What is FAT and SAT ?

The full form of FAT and SAT is Factory Assessment Test and Site Assessment Test

Factory Acceptance Test (FAT) is a formal test performed at the manufacturer’s site to verify that equipment, machines, or systems:Meet technical specifications Function correctly Are ready for delivery and installation at site or not.

Factory Acceptance Test (FAT) is a formal test performed at the manufacturer’s site to verify that equipment, machines, or systems:Meet technical specificationsFunction correctlyAre ready for delivery and installation at site

Purpose of FAT

  • Detect problems before shipment
  • Reduce commissioning time on site
  • Confirm compliance with contract, drawings, and standards
  • Get client approval before dispatch

Typical FAT Scope

Depends on equipment, but usually includes:

1. Documentation Review

  • Approved drawings (GA, wiring, P&ID)
  • Technical specifications
  • Datasheets
  • Software logic / PLC program
  • Manuals (Operation & Maintenance)

2. Visual & Mechanical Inspection

  • Dimensions and layout
  • Material and finish
  • Welding and fabrication quality
  • Alignment and mounting
  • Safety guards and covers
  • Nameplates and tagging

3. Electrical & Instrumentation Checks

  • Wiring as per drawings
  • Cable labelingPanel layout
  • Earthing/grounding
  • Voltage, current ratings
  • Instrument calibration (if applicable)

4. Functional Testing

  • Power ON / OFF
  • Start–stop sequences
  • Manual and automatic modes
  • Interlocks and permissives
  • Alarm and trip functions
  • Emergency stop (E-Stop)

5. Control System / PLC / HMI Testing

  • I/O checking
  • PLC logic verification
  • HMI screens and commands
  • Alarm display and reset
  • Communication (if networked)

6. Performance Testing

  • Capacity/output verification
  • Speed, pressure, temperature checks
  • Load or no-load tests(as per contract requirements)

7. Safety Testing

  • Emergency stop response
  • Safety interlocksLimit switches
  • Compliance with safety standards

8. FAT Punch List

  • Record deviations or issues
  • Corrective actions agreed
  • Responsible person and target date

FAT Documentation / DeliverablesFAT test proceduresCompleted FAT checklistTest results and recordsCalibration certificatesPunch list and closure reportFAT Acceptance Certificate (signed by client)

FAT vs SAT (Quick Difference)FAT → At manufacturer’s factorySAT (Site Acceptance Test) → At actual installation site

Who Attends FAT?Manufacturer / VendorClient or OwnerConsultant / Third-party inspector (if required)

What is SAT?

Site Acceptance Test (SAT) is the final testing carried out at the actual installation site after equipment is:

  • Delivered
  • Installed
  • Connected to utilities and other systems

SAT confirms the system works under real site conditions.

Purpose of SAT

  • Verify correct installation
  • Confirm performance with actual utilities and loads
  • Validate integration with other equipment
  • Achieve final handover and acceptance

SAT Scope

1. Pre-SAT Checks

  • FAT completed and approved
  • All punch points from FAT closed
  • Installation as per approved drawings
  • Utilities available (power, air, water, raw material)
  • Safety clearances approved

2. Mechanical Installation Verification

  • Alignment and leveling
  • Foundation and anchor bolts
  • Piping and ducting connections
  • Lubrication and oil levels
  • Guards and covers installed

3. Electrical & Instrumentation Checks

  • Power supply verification
  • Earthing/grounding continuity
  • Cable termination checks
  • Field instrument calibration
  • Loop checking
  • Signal verification

4. Functional Testing

  • Power ON / OFF
  • Start–stop from local and control room
  • Manual and automatic modes
  • Interlocks and permissives
  • Alarm and trip verification

Leave a Comment